WIRE PRELAUNCH= SCHEDULE: Version of 2/12/99
|
Week of |
Day |
Activity =96 Overall SOC Schedule |
Leads |
|
2/15 |
2/17-19 |
DA practice normal ops session |
Tim, TomB |
|
2/17-19 |
Timeline generation practice session |
Cong, Yi |
|
|
2/17-19 |
Confusion estimation and survey re-plan test |
Joe, Nick, Cong |
|
|
2/16-19 |
Contingency planning |
All |
|
|
2/22 |
2/22 |
DA pipeline delivery and soft S/W freeze |
Tim |
|
Outreach/News/PR planning |
Perry, Nick |
||
|
Meeting with GSFC reps: Ralph Casasanta |
Carol, Tim |
||
|
3/1 |
Launch |