WIRE PRELAUNCH= SCHEDULE: Version of 2/12/99

Week of

Day

Activity =96 Overall SOC Schedule

Leads

2/15

2/17-19

DA practice normal ops session

Tim, TomB

 

2/17-19

Timeline generation practice session

Cong, Yi

 

2/17-19

Confusion estimation and survey re-plan test

Joe, Nick, Cong

 

2/16-19

Contingency planning

All

       

2/22

2/22

DA pipeline delivery and soft S/W freeze

Tim

   

Outreach/News/PR planning

Perry, Nick

   

Meeting with GSFC reps: Ralph Casasanta

Carol, Tim

       

3/1

 

Launch